No limitations were placed on the scope of Internal Audit during 2025/26. p18
Three follow-up audits were completed during 2025/26, all resulting in an improved opinion of reasonable or substantial assurance. p28
2 further sentences of this summary were held back by verification and are not shown. We only publish claims that survived checking against the cited passages.
Show the 2 passages this is based on
- p184.2 No limitations have been placed on the scope of Internal Audit during 2025/26.
- p285.6 Three follow-up audits were completed during 2025/26. All of these resulted in an improved opinion of reasonable or substantial assurance.