The Local Plan, site by site

Representations on the plan closed on Thursday 12 November 2026, the date on the council’s consultation page: Draft Local Plan Regulation 19 stage ↗.

The Local Plan decides where new homes, workplaces and green space go in Hastings for the next fifteen years, and which planning applications the council should approve. This page lists every site in the council's latest draft, by ward, in the plan's words, with a page for each.

The sites

34 sites: 23 for homes, 1,131 net new homes between them, 9 for workplaces and 2 for Gypsy and Traveller pitches. Each site has a page saying what the plan says about it, what a planning application there would have to do, and what people said about it in the spring.

Homes Workplaces Gypsy and Traveller pitches Each light is at the street the site's name or description gives, not its exact boundary, which is on the council's Policies Map ↗. Roads © OpenStreetMap contributors.

By ward: Ashdown (4), Baird (5), Braybrooke (1), Castle (1), Central St Leonards (3), Conquest (2), Gensing (1), Hollington (5), Maze Hill (2), Ore (5), West St Leonards (3), Wishing Tree (2)

Ashdown

Baird

Braybrooke

Castle

Central St Leonards

Conquest

Gensing

Hollington

Maze Hill

Ore

West St Leonards

Wishing Tree

Sites dropped since the spring draft

The spring draft had these sites too. The council's consultation report says why each was taken out.

Read from the plan ↗ and the spring consultation report ↗ with fixed rules. The spring figures are the council's count of comments on each policy.

The plan

The version on this page: Appendix 1 Draft Local Plan - Pre Submission (Regulation 19) September 2026 ↗, Full Council, Wed 23 Sep 2026.

The timetable, in the council's words

What this stage was, and what happens to the comments

Regulation 19 is the last stage before the plan is examined. The council published the plan it intends to submit, and anyone could send comments (called representations) during the publication period, which has closed. They go, with the plan, to an independent planning inspector appointed by the government, who holds an examination.

The inspector's questions are set nationally: whether the plan is legally compliant (prepared the way the law requires), whether it is sound (positively prepared, justified by its evidence, effective, and consistent with national policy), and whether the council met its duty to cooperate with neighbouring councils.

What happens next, step by step, is in the story so far.

The papers

We read the councils' published papers with fixed rules, and no language model is involved on this page. If we've got something wrong, we correct it here and log it on the about page.

Homes built, and the five-year land supply

The Housing Delivery Test

The government's Housing Delivery Test: 2025 measurement, published 17 August 2026, compares the homes built in each council's area over three years with the number required. For Hastings: 1,457 homes required and 646 delivered over 2022-23 to 2024-25: a measurement of 44%. The consequence it gives Hastings: “Presumption”. 93 of the 302 areas measured have the same consequence.

April to March Homes requiredHomes delivered
2022-23481116
2023-24486128
2024-25490402

What the consequences mean, in the National Planning Policy Framework (Annex D, paragraph 12): “Where delivery falls below 95% of the requirement over the previous three years, the authority should prepare an action plan to assess the causes of under-delivery and identify actions to increase delivery in the future;” “Where delivery falls below 85% of the requirement over the previous three years, a buffer of 20% should be added to the identified supply of specific deliverable sites. This is in addition to the requirement for an action plan;” “Where delivery falls below 75% of the requirement over the previous three years, an evidenced unmet need for housing is deemed to exist for the purpose of applying policy S5(1)(j) in this Framework. This is in addition to the requirements for an action plan and 20% buffer.”

The other East Sussex districts
DistrictRequired DeliveredMeasurementConsequence
Eastbourne2,22451323%Presumption
Lewes2,3411,39860%Presumption
Rother2,19777635%Presumption
Wealden3,5983,21789%Action plan

From MHCLG's Housing Delivery Test: 2025 measurement, under the Open Government Licence. Homes delivered count homes built, net of losses, with student and care home bedspaces converted to homes by the government's ratios, so the figures have decimals.

The five-year housing land supply

From the council's Local Plan Monitoring Report 2023-2024 (published February 2025), Table 9, “5 year housing land supply at December 2024”:

(A) Housing Target710
(B) 5-year housing land supply requirement (A x 5)3,550
(C) 5-year housing land supply requirement plus 20% buffer4,260
(D) Supply of deliverable sites (see table 10 and it’s proceeding paragraphs)1,406
(E) % supply (D / C)33%
(F) supply expressed in years (D / C x 5 years)1.65 years

This is the council's latest published figure, at December 2024. The council's monitoring page says: “The new 2024/25 LPMR will be published as soon as possible to include the new 2025 HDT results.” The council's Local Plan monitoring page.

Net new homes each year

The report's Table 2: homes built, net of losses, by April-to-March monitoring year, after the Housing Delivery Test adjustment.

02004006002004/05: 210 net new homes2004/052005/06: 338 net new homes3382006/07: 203 net new homes2007/08: 283 net new homes2008/09: 241 net new homes2008/092009/10: 155 net new homes2010/11: 77 net new homes2011/12: 195 net new homes2012/13: 148 net new homes2012/132013/14: 133 net new homes2014/15: 167 net new homes2015/16: 244 net new homes2016/17: 191 net new homes2016/172017/18: 204 net new homes2018/19: 178 net new homes2019/20: 86 net new homes2020/21: 111 net new homes2020/212021/22: 169 net new homes2022/23: 116 net new homes2023/24: 127 net new homes
The figures as a table
2004/05210
2005/06338
2006/07203
2007/08283
2008/09241
2009/10155
2010/1177
2011/12195
2012/13148
2013/14133
2014/15167
2015/16244
2016/17191
2017/18204
2018/19178
2019/2086
2020/21111
2021/22169
2022/23116
2023/24127