East Sussex Local Growth Assurance Framework (ESLGAF) Capital Programme report
What it recommends
- “note the final spend in 2025/26 for the Local Growth Fund and Growing Places Fund programmes as set out in.”
What the meeting decided
The minutes record: Noted. “RESOLVED to: 1) note the final spend in 2025/26 for the Local Growth Fund and Growing Places Fund programmes as set out in Appendices 1 and 4 of the report; 2) note the project updates that took place across the Local Growth Fund, Growing Places Fund and Getting Building Fund programmes in 2025/26 as set out in Appendices 2, 6 and 7 of the report; 3) agree the forecast scheme spend profile for the Local Growth Fund programme as detailed at Appendix 3 of the report for the 2026/27 financial year; and 4) agree the…” minutes ↗
In plain English
Recommended · This went to the meeting on Fri 24 Jul 2026. What was decided is in that meeting's minutes.
A report from the Director of Communities, Economy and Transport goes to East Sussex County Council's Lead Member for Economy on 24 July 2026. p1p2p38
It sets out project progress and spending on three funds: the Local Growth Fund, the Growing Places Fund and the Getting Building Fund, for 2025/26 and the forecast for 2026/27. p3p4
Officers recommend that the Lead Member note the final 2025/26 spend and project updates, and agree the forecast spending profiles for the Local Growth Fund and Growing Places Fund in 2026/27. p5p6p7p8p9
The report says £2,747,637.15 was spent across four Local Growth Fund projects in 2025/26 against a budget of £7.415m carried forward, with the remaining £4.667m profiled for 2026/27. p22p26
The Queensway Gateway Road and Churchfields Business Centre projects were confirmed as complete in 2025/26. p25
Show the 13 passages this is based on
- p1Report to: Lead Member for Economy Date of meeting:
- p224 July 2026 By: Director of Communities, Economy and Transport
- p3Title: East Sussex Local Growth Assurance Framework (ESLGAF) Capital Programme report Purpose:
- p4To present the project progress, and project spend across the Local Growth Fund, Growing Places Fund and Getting Building Fund for 2025/26 and the forecast for 2026/27.
- p5RECOMMENDATIONS: The Lead Member is recommended to:
- p61) note the final spend in 2025/26 for the Local Growth Fund and Growing Places Fund programmes as set out in Appendices 1 and 4;
- p72) note the project updates that took place across the Local Growth Fund, Growing Places Fund and Getting Building Fund programmes in 2025/26 as set out in Appendices 2, 6 and 7;
- p83) agree the forecast scheme spend profile for the Local Growth Fund programme as detailed at Appendix 3 for the 2026/27 financial year; and
- p94) agree the forecast scheme spend profile for the Growing Places Fund programme as detailed at Appendix 5 for the 2026/27 financial year.
- p222025/26 Programme 2.1 Appendix 1 to this report sets out the final spend for the 2025/26 LGF programme. £ 2,747,637.15 was spent across 4 projects against a baseline budget of £7.415m which had been carried forward from 2024/25. Further details on each of these projects and the current status of all the projects in the LGF programme are outlined at Appendix 2.
- p252.4 The Queensway Gateway Road, and Churchfields Business Centre projects were confirmed as complete in 2025/26 according to the Ministry of Housing, Communities and Local Government (MHCLG) definition of all financial, practical and output targets being achieved.
- p262026/27 Programme 2.5 The remaining £4.667m of LGF funding is profiled to be spent in 2026/27 as outlined in Appendix 3. This figure represents the forecast spend at the beginning of the 2026/27 financial year.
- p38RUPERT CLUBB Director of Communities, Economy and Transport Contact Officer: Rupert Clubb Email: Rupert.Clubb@eastsussex.gov.uk
Places and organisations it names
Other papers for this meeting
- Lead Member for Economy agenda
- Appendix 1, Lead Member for Economy
- Appendix 2, Lead Member for Economy
- Appendix 3, Lead Member for Economy
- Appendix 4, Lead Member for Economy
- Appendix 5, Lead Member for Economy
- Decisions made by the Lead Cabinet Member on 17 March 2026
- Lead Member for Economy minutes (draft)
- WorkWell programme coordination in partnership with Surrey County Council and Surrey and Sussex Integrated Care Board