This appendix sets out the final spend for the 2025/26 Local Growth Fund (LGF) programme, together with mitigation, and covers only LGF investment rather than other contributions to each scheme. p1

Across all the schemes listed, the total LGF allocation for all years is £82,019,667, with £7,414,637.15 carried forward from 2024/25 and £2,747,637.15 recorded as final spend in 2025/26. p18

The Hastings and Bexhill movement and access package has a total LGF allocation of £9,000,000, with £3,840,868.57 carried forward from 2024/25 and £838,868.57 spent in 2025/26. p5p6

Other schemes with spend in 2025/26 include the Eastbourne town centre LSTF access and improvement package at £1,667,689.66, the Eastbourne and South Wealden walking and cycling LSTF package at £183,450.14, and the Hailsham, Polegate and Eastbourne movement and access transport scheme at £57,628.78. p2p3p4p5

1 further sentence of this summary was held back by verification and is not shown. We only publish claims that survived checking against the cited passages.

Show the 7 passages this is based on
  • p1Appendix 1: 2025/26 Local Growth Fund (LGF) Programme: Final Spend and Mitigation * Figures provided below relate only to LGF investment and do not include other scheme contributions
  • p2Scheme Total LGF Allocation all Years (£) LGF carried forward from 24/25 (£) LGF Final Spend in 25/26 (£) Hailsham/Polegate/Eastbourne movement and access transport scheme
  • p32,100,000 57,628.78 57,628.78 Eastbourne and South Wealden walking and cycling LSTF package
  • p46,600,000 1,848,450.14 183,450.14 Eastbourne town centre LSTF access and improvement package
  • p58,000,000 1,667,689.66 1,667,689.66 Hastings and Bexhill movement and access package
  • p69,000,000 3,840,868.57 838,868.57 Sovereign Harbour (aka site infrastructure investment)
  • p181,440,000 - - Total 82,019,667 7,414,637.15 2,747,637.15