In the report's words. A recommendation is a proposal, and the meeting can agree, change or reject it.

What the meeting decided

The minutes record: Agreed. “RESOLVED: To ratify the urgent delegated decision that was made in March 2026 to allocate £50,000, to undertake work needed to create the building works tender pack for the White Rock Baths. To approve the delegation of authority to the Deputy Chief Executive, or her nominee, in consultation with the Chair of the Charity Committee, to allocate up to £1.5 million for works to the White Rock Baths, as outlined in point 5 in the main report.” minutes ↗

In plain English

Each sentence was checked against the passage it cites. How the checking works.

Recommended · This went to the meeting on Mon 22 Jun 2026. What was decided is in that meeting's minutes.

A report recommends ratifying an urgent delegated decision made in March 2026 to allocate £50,000 to prepare a building works tender pack for White Rock Baths. p3

It also recommends delegating authority to the Deputy Chief Executive, in consultation with the Chair of the Charity Committee, to allocate up to £1.5 million for the works. p4

Planned work includes tackling water getting in from the promenade and concrete repairs to the main skate park, central block and courtyard areas. p7p8

We’ve left out 1 more sentence of this summary because it didn’t pass our check against the paper.

Show the 4 passages this is based on
  • p3Recommendation(s) 1. To ratify the urgent delegated decision that was made in March 2026 to allocate £50,000, to undertake work needed to create the building works tender pack for the White Rock Baths. page 1 ↗
  • p42. To approve the delegation of authority to the Deputy Chief Executive, or her nominee, in consultation with the Chair of the Charity Committee, to allocate up to £1.5 million for works to the White Rock Baths, as outlined in point 5 in the main report. page 1 ↗
  • p7• Management of water ingress from the promenade, alongside prioritised internal reactive concrete repair works, including the removal of loose or potentially dangerous areas within the main skate park. page 1 ↗
  • p8• Targeted concrete repair and maintenance works within the Central block and Courtyard areas. page 1 ↗