The Audit Committee noted the Internal Audit Progress Report for Quarter 1 (April to June 2026), which said three audits had been completed and that implementation of the high-priority management actions it set stood at 60%. p5p6

The Committee noted the Treasury Management Update for 2026/27 Quarter 1, which reported that activities had been carried out in full compliance with the Council's Treasury Management Strategy, with no breaches of treasury or prudential indicators. p7p8

The Committee considered a proposal to reschedule six Public Works Loan Board loans worth a total of £11 million, and recommended that Full Council approve the proposal for implementation during 2026/27. p7p8

The Committee noted the Grant Thornton Regaining Assurance Strategy, which set out a pathway towards an unmodified audit opinion by 2027/28 following disclaimer audit opinions for the financial years 2021/22 to 2024/25. p9p10

It also noted progress on the Council's 2025/26 external audit, with findings expected to be reported to the Committee in December 2026. p10

Show the 6 passages this is based on
  • p523. Internal Audit Progress Report - Quarter 1 (April 2026 - June 2026) Mark Winton, Chief Internal Auditor, presented the report summarising audit work completed during Quarter 1. Members were advised that three audits had been completed comprising Payroll Follow-Up, User Access Management (Unit4) and Officer Declarations of Interest and Gifts and Hospitality Follow-Up. Two audits had received Reasonable Assurance opinions whilst the User Access Management audit received a Partial Assurance opinion. The report also highlighted that implementation of agreed high-priority management actions stood at 60%. Mr Winton advised that whilst overall delivery of the annual audit plan was behind profile due to the commencement of several large and complex reviews, he remained confident that sufficient work would be completed during the year to provide an annual audit opinion. He further advised that the Council remained on track for an overall Partial Assurance opinion, with improvements being delivered through actions contained within the Annual Governance Statement. Members discussed findings from the User Access Management audit and expressed concern regarding historic access permissions remaining active after individuals had left the authority. Questions were raised regarding whether the matter constituted a data breach and whether arrangements had since been strengthened. Officers confirmed there was no evidence of a data breach and advised that Information Technology officers had undertaken significant work to address the issue. Members were reassured that agreed audit actions would be monitored and subject to future audit follow-up. The Chair welcomed the progress made in strengthening governance and internal controls over recent years and thanked officers and the Internal Audit team for their continued work supporting improvement across the authority.
  • p6RESOLVED: That the contents of the quarterly report be noted and the Committee consider any further action required in response to the issues raised. Reason for Recommendation : i ) To support the Committee's responsibilities for assessing the effectiveness of the internal control environment and the effectiveness of the Internal Audit Service. ii) To comply with the requirements set out in the Global Internal Audit Standards. page 2 ↗
  • p724. Treasury Management Update- 2026/27 Quarter 1 Ola Owolabi, Deputy Chief Finance Officer, presented the report. Members were advised that Treasury Management activities during Quarter 1 had been undertaken in full compliance with the Council's approved Treasury Management Strategy and CIPFA requirements, with no breaches of treasury or prudential indicators reported. The General Fund treasury position remained on budget and no external borrowing had been undertaken during the quarter. Members considered the Council's external borrowing position and the proposal to reschedule six Public Works Loan Board loans with a total value of £11 million. Officers explained that favourable market conditions presented an opportunity to secure an early repayment discount valued at approximately £5.048 million, potentially generating lifetime savings of £2.311 million whilst reducing the Council's long-term debt obligations. Members questioned the funding options available to facilitate the proposal, including the use of earmarked reserves, General Fund balances or replacement borrowing. Detailed explanations were provided regarding the advantages and disadvantages of each option and the need to undertake further financial analysis before implementation. Discussion also took place regarding the impact of economic uncertainty and market conditions upon treasury management activity. Officers advised that market movements could affect the final value of savings available through debt rescheduling and would continue to be monitored carefully. The Committee additionally considered the emerging concept of Community Municipal Investment (CMI) as an alternative mechanism for financing environmental and social infrastructure projects. Members welcomed the potential opportunities for direct community investment and engagement. page 2 ↗
  • p8Following discussion, Members requested that officers invite specialist advisers to a future meeting to provide a detailed presentation on successful CMI schemes operating elsewhere in the country and to explore opportunities for site visits. RESOLVED: That the report and the assurances contained within it, that activities have been undertaken in accordance with the approved Treasury Management Strategy, be noted and recommended to Full Council. That approval of the Debt Rescheduling proposal for implementation during 2026/27 be recommended to Full Council. Reasons for Recommendation: i ) To ensure Members are aware of the activities undertaken during the quarter. ii) To ensure the relevant Codes of Practice have been complied with. iii) To ensure the Treasury Management Strategy remains effective and does not currently require revision. page 3 ↗
  • p925. Regaining Assurance Strategy for Hastings Borough Council Ola Owolabi, Deputy Chief Finance Officer, introduced the report and invited representatives from Grant Thornton to present the Regaining Assurance Strategy. Members were advised that the strategy had been prepared following disclaimer audit opinions issued for the financial years 2021/22 to 2024/25 and set out the pathway towards achieving an unmodified audit opinion by 2027/28. Members heard that the Council had been assessed as a Category B authority under the MHCLG capacity assessment framework, meaning a return to full audit assurance remained achievable within the national build-back period, albeit with operational and technical challenges. The anticipated trajectory was for a disclaimer opinion in respect of 2025/26, a qualified opinion in 2026/27 and an unmodified opinion in 2027/28, subject to successful delivery of the agreed programme of work. Ade O Oyerinde of Grant Thornton advised that priority would be given to completing the 2025/26 audit by the end of November 2026, following which detailed assurance rebuilding work would commence. Particular attention would be given to historic balances, reserves and matters relating to the former housing company, which remained one of the key areas capable of affecting the anticipated trajectory. In response to a question from Councillor Drew regarding the Category B assessment, Members were advised that the MHCLG framework comprised four categories ranging from Category A through to Category D, with Category B reflecting authorities capable of achieving ISA-compliant audit assurance despite operational challenges. Members welcomed the progress made and commended the work undertaken by officers and auditors in progressing the Council's financial governance arrangements and restoring audit assurance. page 3 ↗
  • p10Councillor Webb welcomed the Category B assessment and recognised the significant work undertaken by officers to strengthen financial governance and support the assurance recovery process. Officers also updated the Committee on progress with the 2025/26 external audit and advised that audit findings were expected to be reported to the Committee in December 2026. RESOLVED: 1. That the Grant Thornton Regaining Assurance Strategy be noted. 2. That progress on the 2025/26 final audit be noted. Reasons for Recommendation: i ) To advise the Committee of Grant Thornton's plan to restore audit assurance following disclaimer audit opinions for the years 2021/22 to 2024/25. ii) To update the Committee on progress with the 2025/26 audit. page 4 ↗