Ashdown Forest Trust Fund

Committee report · Cabinet · Wed 24 Sep 2025 · East Sussex County Council · the whole meeting

Read the council's document ↗

What it recommends

In the report's words. A recommendation is a proposal, and the meeting can agree, change or reject it.

What the meeting decided

The minutes record: Agreed. “RESOLVED to: 1) note the report and the Ashdown Forest’s Trust Income and Expenditure Account for 2024/25 and Balance Sheet as at 31 March 2025; and 2) approve the draw of £99,200 from the General Reserve to fund a programme of tree surveys and works across the forest. Reason 20.3 The Trust made an operating surplus of £9,062 during 2024/25. The General Reserve as at 31 March 2025 amounts to £188,346. This fund is available to finance expenditure which meets the Trust’s objectives.” minutes ↗

In plain English

Each sentence was checked against the passage it cites. How the checking works.

Recommended · This went to the meeting on Wed 24 Sep 2025. What was decided is in that meeting's minutes.

The Ashdown Forest Conservators identified a £113,700 programme of tree surveys and works across the forest, and have requested that the remaining £99,200 be drawn from the General Reserve to fund it. p21p22p23

Officers recommend that Cabinet note the report and the Trust's accounts, and approve the draw of £99,200 from the General Reserve to fund the tree survey and works programme. p5p6p7

We’ve left out 2 more sentences of this summary because they didn’t pass our check against the paper.

Show the 6 passages this is based on
  • p5RECOMMENDATIONS Cabinet is recommended to: page 1 ↗
  • p61) note the report and the Ashdown Forest’s Trust Income and Expenditure Account for 2024/25 and Balance Sheet as at 31 March 2025; and page 1 ↗
  • p72) approve the draw of £99,200 from the General Reserve to fund a programme of tree surveys and works across the forest. page 1 ↗
  • p212.10. The Conservators have provided the information at Appendix 3, which highlights a £113,700 programme of tree surveys and works required across the forest. page 2 ↗
  • p222.11. The Conservators have already carried out the work defined as very urgent and urgent, leaving £107,200 outstanding, of which a further £8,000 will be covered by the Conservator’s budget. page 2 ↗
  • p232.12. The Conservators have requested to draw the remaining £99,200 from the General Reserve. page 2 ↗