Proposed relocation of Hastings Register Office

Committee report · Lead Member for Transport and Environment · Mon 10 Nov 2025 · East Sussex County Council

Read the council's document ↗

What it recommends

In the report's own words. A recommendation is a proposal: the meeting can agree, change or reject it.

What the meeting decided

The minutes record: Agreed. “RESOLVED to: (1) approve the proposal to move Hastings Register Office (“the Service”) to Hastings Library, subject to planning permission, to facilitate service delivery improvements and deliver revenue savings of £100K.” minutes ↗

In plain English

Each sentence was checked against the passage it cites; how the checking works.

Recommended · This went to the meeting on Mon 10 Nov 2025. What was decided is in that meeting's minutes.

The report proposes relocating Hastings Register Office for births, deaths, and marriages to Hastings Library, to improve service delivery, optimise use of Council assets and improve accessibility. p4

Officers recommended that the Lead Member approve the proposal to move Hastings Register Office to Hastings Library, subject to planning permission, to deliver revenue savings of £100K. p6

The estimated cost of relocating Hastings Register Office is £125K, based on pre-tender estimates. p35

1 further sentence of this summary was held back by verification and is not shown. We only publish claims that survived checking against the cited passages.

Show the 3 passages this is based on
  • p4Purpose: This report proposes the relocation of Hastings Register Office for births, deaths, and marriages to the Hastings library building. The move aims to enhance service delivery, optimise use of Council assets, and improve accessibility for residents.
  • p6(1) Approve the proposal to move Hastings Register Office (“the Service”) to Hastings Library, subject to planning permission, to facilitate service delivery improvements and deliver revenue savings of £100K. The savings that would be delivered through the relocation of the Service would contribute to the Medium-Term Financial Plan (MTFP) savings in 2026/2027 and 2027/2028;
  • p352.18 A draft programme has been developed and costed and the estimated costs associated with the relocation of the Hastings Register Office, based on pre-tender estimates, are £125K. Should the Lead Member endorse the recommendations in this report, the Registration Service would be operational from Hastings Library in September 2026. This programme would ensure service continuity and a smooth coordinated relocation with minimal disruption to users.

Places and organisations it names

Other papers for this meeting

The council's document is the record; this page collects what Open Hastings knows about it. If something here is wrong, it is corrected in place and logged on the about page.