Appendix 3: 2025-26 PIER Savings P7
In plain English
Noted · Received for information; no decision followed.
The council's savings programme for 2025/26 targeted £429,500 in net savings, of which £429,500 (100%) had been achieved by Period 7. p11
A £12,500 saving was identified from moving council services to cashless operations, following earlier consultation. p11
Show the 1 passage this is based on
- p112. Cashless operations To continue with the previously consulted on (and Council approved) approach to delivering services on a cashless basis to save costs on cash collection contract. Individual service areas will be consulted on in terms of timelines and transition options and approach to avoid service delivery issues and loss of income. £12,500 £12,500 Green Saving achived Total Net Savings £429,500 £429,500 100% page 2 ↗
Places and organisations it names
Other papers for this meeting
- 2025-26 P7 Financial Update Report to end of October 2025
- 2026 Hastings Climate Strategy
- Cabinet agenda
- Appendix 1: Budget Monitoring Tables 2025-26 P7 October 2025
- Appendix 2: P7 2025-26 Capital Monitoring
- Appendix B: Climate Change Actions Log 2025-30
- Jan 2026 Climate Update Report to Cabinet
- Minutes of Cabinet, 1 December 2025
- Museum minutes 24.11.25
- Museum report January 2026
- Pay Policy 2026-2027
- Pay Policy Report 2026-2027 update
- Cabinet minutes