Review of Strategic Highway Policies and Asset Management Plans
What it recommends
- “Note the outcomes of the strategic review process.”
- “Approve the revised versions of the: a) Highways Asset Management Policy as set out at Appendix 3; b) Highway Infrastructure Asset Management Strategy as set out at Appendix 4; c) Highway Network Resilience Plan as set out at Appendix 8; d) Highways Drainage Asset Management Policy as set out in Appendix 5; and e) Drainage Asset Management Plan (DAMP) as set out at Appendix 6.”
- “Approve the implementation of new policies: a) Commuted Sums Policy and Guidance Note as set out at.”
What the meeting decided
The minutes record: Agreed. “RESOLVED to: (1) Note the outcomes of the strategic review process; (2) Approve the revised versions of the: a) Highways Asset Management Policy as set out at Appendix 3 of the report; b) Highway Infrastructure Asset Management Strategy as set out at Appendix 4 of the report; c) Highway Network Resilience Plan as set out at Appendix 8 of the report; d) Highways Drainage Asset Management Policy as set out in Appendix 5 of the report; and e) Drainage Asset Management Plan (DAMP) as set out at Appendix 6 of the…” minutes ↗
In plain English
Recommended · This went to the meeting on Mon 8 Sep 2025. What was decided is in that meeting's minutes.
Officers recommended that the Lead Member for Transport and Environment note the outcomes of a review of East Sussex County Council's strategic highway policies and asset management plans. p5p6
The review covered the Highways Asset Management Policy, Highway Infrastructure Asset Management Strategy, Highway Network Resilience Plan, Highways Drainage Asset Management Policy and Drainage Asset Management Plan. p8p9p10p11p12
Officers also recommended approving two new policies: a Commuted Sums Policy and Guidance Note, and a Winter Service Policy. p14p15
The report said no additional funding was required, with the changes to be delivered within existing budgets and staffing resources. p18p23
Show the 11 passages this is based on
- p5RECOMMENDATIONS: The Lead Member is recommended to:
- p6(1) Note the outcomes of the strategic review process
- p8a) Highways Asset Management Policy as set out at Appendix 3;
- p9b) Highway Infrastructure Asset Management Strategy as set out at Appendix 4;
- p10c) Highway Network Resilience Plan as set out at Appendix 8;
- p11d) Highways Drainage Asset Management Policy as set out in Appendix 5; and
- p12e) Drainage Asset Management Plan (DAMP) as set out at Appendix 6;
- p14a) Commuted Sums Policy and Guidance Note as set out at Appendices 9 and 10; and
- p15b) Winter Service Policy as set out at Appendix 11
- p18No additional funding is required and maintaining Band 3 status under the DfT Incentive Fund will continue to secure the maximum level of highways funding available to the Council. 1.6. In practical terms, these changes mean better prioritisation of maintenance works, stronger planning for severe weather, improved drainage management to reduce flooding, and clearer communication with residents and Councillors about how decisions are made. 2. Supporting Information Element 1: Revisions to the Asset Management Policy and Highway Infrastructure Asset Management Strategy 2.1. Summary of Formatting Enhancements – These formatting refinements collectively aim to make the documents more user-friendly for Council Members, operational teams, and the public, promoting improved understanding, consistent implementation, and transparent governance. To enhance the usability and professionalism of the strategic highway documents, the following formatting changes have been implemented: · Consistent Document Structure : All documents now follow a standard format with clearly defined sections, headings, and subheadings. This consistent structure improves navigation and enables users to locate information quickly and intuitively. · Unified Terminology and Style : Terminology and acronyms have been standardised across all documents to avoid confusion and maintain a professional tone. · Improved Referencing and Cross-Referencing: Citations of legislation, standards (including ISO 55000), and internal documents have been updated and formatted uniformly. Cross-references within and between documents have been added or improved to reinforce coherence and ease of use.
- p233. Conclusion and Reasons for Recommendations 3.1. This scheduled review forms part of the Council’s planned cycle of strategic document updates. It builds on the established and effective framework provided by the existing strategic highway policies and asset management plans, ensuring they remain fit for purpose and aligned with current legislation, national guidance and recognised best practice. The review is a proactive measure to maintain clarity, consistency, and transparency in the Council’s approach. 3.2. Approval of the revised documents and new targeted policies will: · Maintain the Council’s DfT Incentive Fund Band 3 status, securing the highest level of funding available. · Provide clear, documented frameworks for decision-making, complementing the robust approaches already in place. · Strengthen planning for severe weather, enhance drainage management, and ensure investment priorities are based on risk and whole-life value. · Formalise a consistent, transparent approach to developer contributions through the Commuted Sums Policy; and · Establish a clear basis for responding to future winter service network requests without altering existing agreed routes, ensuring continuity while improving clarity. 3.3. These updates will not reduce service levels or change existing commitments, and no additional funding is required. They have been developed entirely within existing budgets and staffing resources and are designed to strengthen the Council’s asset management approach, improve operational practicality, and provide greater transparency for Members, staff and the public. 3.4. The revisions and new policies reflect developments in legislation, national guidance, and asset management practice, and have been informed by benchmarking with other high-performing authorities and the Council’s own advancements in asset management maturity.
Places and organisations it names
Other papers for this meeting
- Lead Member for Transport and Environment agenda
- Appendix 1, Lead Member for Transport and Environment
- Appendix 1, Lead Member for Transport and Environment
- Appendix 1, Lead Member for Transport and Environment
- Appendix 2, Lead Member for Transport and Environment
- Appendix 2, Lead Member for Transport and Environment
- Appendix 3, Lead Member for Transport and Environment
- Appendix 4, Lead Member for Transport and Environment
- Appendix 5, Lead Member for Transport and Environment
- Decisions made by the Lead Cabinet Member on 16 June 2025
- East Sussex Local Transport Plan 4 (LTP4) - Funding Request Assessment Process
- Highway Maintenance Incentive Funding 2025/26
- Petition to stop Stagecoach changing the 51 bus service to Eastbourne from half hourly to hourly
- Lead Member for Transport and Environment minutes