The plan proposes five objectives for managing property assets: meeting the Council's statutory purpose, working in partnership, adding community value, enhancing asset performance and resilience, and maintaining a strategic and affordable property portfolio. p25p30p32p34p37
The Council's portfolio covers over 9,000 plots of land and around 400 building assets, with a current book value of over £800 million, including about 225 freehold buildings and around 55 rented premises. p20p74
For surplus assets, the plan describes a framework of options to work through case by case: alternative Council use, partnership use, interim or income-generating use, community use or transfer, and disposal. p88p89p90p91p92p93
The document names the proposed approval route as the Lead Member for Resources and Climate Resilience, with a proposed approval date of 8 December 2026, and says the plan will be reviewed annually. p3p4p6
Show the 16 passages this is based on
- p3Property Approval route Lead Member for Resources and Climate Resilience page 2 ↗
- p4Proposed approval date 8th December 2026 page 2 ↗
- p6Reviewed annually and updated as required page 2 ↗
- p202. Introduction Local authorities across the UK hold large property portfolios (assets made up of buildings and land) which have been acquired, gifted or inherited over many years. East Sussex County Council (ESCC) is no different, owning or operating over 9,000 plots of land (including highways) and approximately 400 building assets. To achieve ESCC’s goals, we want to use all our resources as effectively and efficiently as possible, including our land and buildings. page 5 ↗
- p25OBJECTIVE 1 Meeting the Council’s statutory purpose page 5 ↗
- p30OBJECTIVE 2 Working in partnership To promote joint working w ith partners where it will provide benefits for service delivery and in securing efficiencies. page 6 ↗
- p32OBJECTIVE 3 Adding community value To recognise and consider the potential community value of Council property assets. page 6 ↗
- p34OBJECTIVE 4 Enhancing asset performance, resilience and long-term sustainability page 6 ↗
- p37OBJECTIVE 5 Maintaining a strategic and affordable property portfolio page 7 ↗
- p74· Property Environmental Performance Statement 4. Asset management strategy 4.1. Our land and buildings The Council’s portfolio comprises offices, libraries, day centres, care facilities, depots, schools, assets leased to community organisations and properties held to generate commercial income. The performance of each asset is linked to the strategic purpose for holding it. Assets deliver a mixture of frontline services, indirect service provision (back office), and help support local communities. Retaining assets as part of ESCC’s property portfolio is based on their contribution to service delivery, community benefit and strategic priorities. Through ongoing engagement with frontline services, the Property Team helps ensure that the estate evolves alongside changing service requirements, supporting innovative and sustainable approaches to how services are delivered both now and in the future. The Council’s property portfolio has over 9,000 land and building assets, with a current total book value of over £800 million. This is the amount that is included within the authority’s accounts and is not the exact amount that ESCC would receive when selling its assets. It does however demonstrate what a considerable resource the Council’s land and buildings are, and why these need to be carefully managed to avoid wasting public money by retaining buildings which are not fit for purpose. The Council currently holds approximately 225 freehold buildings and of these, around 130 are directly managed by ESCC. In addition to this figure, ESCC also occupies approximately 55 rented premises which it may have full or part responsibility for the maintenance of, under the terms of the occupation agreement. As the way the Council delivers its services evolves, its asset portfolio will also need to change. page 10 ↗
- p88Reviews are undertaken collaboratively with service departments, drawing on property performance information, service requirements, financial considerations and opportunities for alternative uses. They inform decisions on continued occupation, investment, improvement, sharing, repurposing or potential disposal of assets. Where assets are no longer required for their existing purpose, the Council will consider their future use in the context of wider corporate priorities, including opportunities to support other services, community outcomes, partnership working and the generation of capital receipts or income, where appropriate. The outcomes of asset reviews are considered through the Council’s internal governance arrangements, with proposals progressing through the relevant constitutional decision-making processes. Elected members are engaged throughout the process, particularly where proposals have strategic, financial, service delivery or community implications. 5.3. Decision-making framework The Council will evaluate the future options for a surplus asset before making recommendations. The decision-making framework below provides a basis for considering potential options rather than a requirement to exhaust each option sequentially or a presumption in favour of any particular outcome. The extent to which each option is explored will be proportionate to the circumstances of the asset, with decisions informed by financial, operational, community and wider strategic considerations. Further operational detail on how surplus assets are assessed and managed is set out in the Council’s Estates Management Statement: page 17 ↗
- p89· Alternative Council use: seek to utilise the asset for an alternative or emerging operational Council purpose, supporting statutory and service requirements and potentially avoiding the need to acquire or lease additional property. Where an asset becomes available, relevant services will be consulted to identify any existing or emerging operational requirements. page 18 ↗
- p90· Partnership use : explore whether the asset could be utilised by other public-sector partners. This may provide opportunities to share service delivery, improve utilisation, generate income or efficiencies, and support the continued delivery of public services within local communities. page 18 ↗
- p91· Interim or income-generating use: consider whether the asset can be let commercially, including in the short-term (‘meanwhile use’). This could allow income generation, offset holding costs and preserve the asset for potential future strategic use. page 18 ↗
- p92· Community use or transfer: consider whether there is a viable and sustainable community or third-sector use for the asset. This may include occupation or acquisition on commercial terms as well as, where justified, Community Asset Transfer. Consideration of community use does not create a presumption in favour of transfer or disposal at less than market value and will take account of financial viability, deliverability, the Council's statutory and financial responsibilities, and wider strategic objectives. page 18 ↗
- p93· Disposal: where disposal represents the most appropriate outcome, consider the sale of the asset to reduce ongoing liabilities, generate a capital receipt and support the Council's wider capital and financial objectives. Energy efficiency, climate resilience, asset condition, statutory compliance, financial implications and future strategic requirements will be considered throughout the assessment. 6. Measuring performance To effectively understand how ESCC’s assets are performing, they must continually be evaluated on how they are utilised. Key performance indicators (KPI) are used to report on the performance of the estate, including running costs for the corporate office portfolio, income generation and energy efficiency performance. To help track performance against operational targets set for a given year, the asset management system is used to report on KPIs on the following criteria: page 19 ↗
Places and organisations it names
Other papers for this meeting
- APPENDIX 2: Financial Expenditure and Forecast Outturn
- Place Scrutiny Committee agenda
- Appendix 1: Place Scrutiny HWRS review findings
- Appendix 1: QGR final design and construction phasing (R1.2)
- Appendix 2: Terms of Reference HWRS booking system review
- Appendix 2 ESCC Property Asset Register October 26
- Appendix 3 SPACES Programme Update November 26
- ESCC Strategic Asset Plan 2026-2029 and related Property service updates
- Forward Place decisions 30 Nov 2026
- Minutes of the previous meeting
- Place Committee work programme November 2026
- Printed plan Forward Plan 1 November 2026 - 28 February 2027 Forward Plan
- Queensway Gateway Road - Post Project Appraisal
- Scrutiny Review of the Household Waste Recycling Site booking system
- Work programme