APPENDIX 2: Financial Expenditure and Forecast Outturn

Committee report · Place Scrutiny Committee · Mon 30 Nov 2026 · East Sussex County Council · agenda item 7 · the whole meeting

The council’s title for this paper: “APPENDIX 2 - Financial Expenditure and Forecast Outturn final”.

Read the council's document ↗

In plain English

Each sentence was checked against the passage it cites. How the checking works.

Noted · Received for information; no decision followed.

Recorded expenditure reached £7,381,697 by 31 March 2026, with a further £500,303 close-out provision identified for 2026/27, giving an indicative cumulative total of £7,882,000. p7p8p9p10

The road opened on 30 September 2025, but movement found in the western embankment soil retention system and outstanding National Highways snagging and completion matters have meant further close-out costs and work continuing into 2026/27. p26

We’ve left out 3 more sentences of this summary because they didn’t pass our check against the paper.

Show the 5 passages this is based on
  • p7Cumulative expenditure to 31 March 2026 £7,381,697 page 1 ↗
  • p82026/27 close-out provision/commitments (Subject to Change) page 1 ↗
  • p9£500,303 Indicative cumulative project expenditure page 1 ↗
  • p10£7,882,000 QUEENSWAY GATEWAY ROAD BUDGET (FUNDING): page 1 ↗
  • p26Additional corrective work - 2026/27 The road opened on 30 September 2025, but that did not mean all contractual, technical, and adoption-related items had been closed. Following a period of extreme weather, movement was identified in the western embankment soil retention system, requiring investigation and stabilisation works. National Highways (NH) also identified outstanding snagging and completion matters. These activities, together with associated project management, professional and contract close-out co sts, have extended into 2026/27. The current close-out provision is £0.5m (subject to change). This is a combined provision for identified commitments, not a cost attributed solely to the embankment. The final amount remains subject to completion, commercial assessment and final-account agreement; responsibility for individual defects should not be inferred from this financial summary. The provision represents an overall project-level forecast and should not be taken as the final amount payable under the NEC4 Option C contract. The contractual treatment of individual costs remains subject to the relevant contract terms and outstanding assessments. page 4 ↗

Places and organisations it names

Other papers for this meeting

This page collects what Open Hastings knows about the council's document. If something here is wrong, we correct it here and log it on the about page.