APPENDIX 2: Financial Expenditure and Forecast Outturn
The council’s title for this paper: “APPENDIX 2 - Financial Expenditure and Forecast Outturn final”.
In plain English
Noted · Received for information; no decision followed.
Recorded expenditure reached £7,381,697 by 31 March 2026, with a further £500,303 close-out provision identified for 2026/27, giving an indicative cumulative total of £7,882,000. p7p8p9p10
The road opened on 30 September 2025, but movement found in the western embankment soil retention system and outstanding National Highways snagging and completion matters have meant further close-out costs and work continuing into 2026/27. p26
Show the 5 passages this is based on
- p7Cumulative expenditure to 31 March 2026 £7,381,697 page 1 ↗
- p82026/27 close-out provision/commitments (Subject to Change) page 1 ↗
- p9£500,303 Indicative cumulative project expenditure page 1 ↗
- p10£7,882,000 QUEENSWAY GATEWAY ROAD BUDGET (FUNDING): page 1 ↗
- p26Additional corrective work - 2026/27 The road opened on 30 September 2025, but that did not mean all contractual, technical, and adoption-related items had been closed. Following a period of extreme weather, movement was identified in the western embankment soil retention system, requiring investigation and stabilisation works. National Highways (NH) also identified outstanding snagging and completion matters. These activities, together with associated project management, professional and contract close-out co sts, have extended into 2026/27. The current close-out provision is £0.5m (subject to change). This is a combined provision for identified commitments, not a cost attributed solely to the embankment. The final amount remains subject to completion, commercial assessment and final-account agreement; responsibility for individual defects should not be inferred from this financial summary. The provision represents an overall project-level forecast and should not be taken as the final amount payable under the NEC4 Option C contract. The contractual treatment of individual costs remains subject to the relevant contract terms and outstanding assessments. page 4 ↗
Places and organisations it names
Other papers for this meeting
- Place Scrutiny Committee agenda
- Appendix 1: Place Scrutiny HWRS review findings
- Appendix 1: QGR final design and construction phasing (R1.2)
- Appendix 1 ESCC Proposed Revised Strategic Asset Plan 2026-2029
- Appendix 2: Terms of Reference HWRS booking system review
- Appendix 2 ESCC Property Asset Register October 26
- Appendix 3 SPACES Programme Update November 26
- ESCC Strategic Asset Plan 2026-2029 and related Property service updates
- Forward Place decisions 30 Nov 2026
- Minutes of the previous meeting
- Place Committee work programme November 2026
- Printed plan Forward Plan 1 November 2026 - 28 February 2027 Forward Plan
- Queensway Gateway Road - Post Project Appraisal
- Scrutiny Review of the Household Waste Recycling Site booking system
- Work programme