Appendix 1: QGR final design and construction phasing (R1.2)
In plain English
Noted · Received for information; no decision followed.
The scheme is split into phases: remedial and link works covering Phase 1, Phase 2a, Phase 2a+ and a temporary ramp, and the main A21/Whitworth Road signalised junction and its connection forming Phase 2b. p3p4
The remaining work needed to finish the design was put at about £2.5m, made up of £2.3m for the Phase 2b junction works and £0.22m for the Phase 1, 2a and temporary ramp works, with the junction figure independently checked by WSP engineering consultants. p6
A timeline covers the scheme's key funding, sign-off and construction milestones, including the road opening on 30 September 2025, and shows further work continuing after that, covering snagging, safety actions, corrective works, hand-over and certification through to November 2026. p8p9
Show the 5 passages this is based on
- p3Remedial and link works Phase 1 (Yellow outline); Phase 2a (Green outline); Phase 2a+ (Blue outline); Temp Ramp (Pink outline) page 1 ↗
- p4The main A21/Whitworth Road signalised junction and associated connection Red outline: Phase 2b page 1 ↗
- p6QGR construction design The remaining activities to complete the development shown in the Figure 2 design were estimated at approximately £2.5m: £2.3m for the main A21/Whitworth Road signalised junction and associated connection (Phase 2b) and £0.22m for remedial and link works (Phases 1, 2a & Temp). WSP engineering consultants independently benchmarked the main works estimate. The revised junction approach avoided the unresolved land requirements of the earlier roundabout proposal. page 1 ↗
- p8QGR construction Journey (Timeline) Figure 3 summarises QGR’s key funding, approval and construction milestones, from initial approval and third-party delivery to County Council intervention and the road opening on 30 September 2025. page 2 ↗
- p9The timeline extends beyond opening, covering the full project lifecycle through to November 2026 , including snagging, safety actions, corrective works, handover, adoption, certification and close-out. Road opening was a major milestone, not formal project completion. page 2 ↗
Places and organisations it names
Other papers for this meeting
- APPENDIX 2: Financial Expenditure and Forecast Outturn
- Place Scrutiny Committee agenda
- Appendix 1: Place Scrutiny HWRS review findings
- Appendix 1 ESCC Proposed Revised Strategic Asset Plan 2026-2029
- Appendix 2: Terms of Reference HWRS booking system review
- Appendix 2 ESCC Property Asset Register October 26
- Appendix 3 SPACES Programme Update November 26
- ESCC Strategic Asset Plan 2026-2029 and related Property service updates
- Forward Place decisions 30 Nov 2026
- Minutes of the previous meeting
- Place Committee work programme November 2026
- Printed plan Forward Plan 1 November 2026 - 28 February 2027 Forward Plan
- Queensway Gateway Road - Post Project Appraisal
- Scrutiny Review of the Household Waste Recycling Site booking system
- Work programme