Queensway Gateway Road - Post Project Appraisal
What it recommends
- “Note the findings and conclusions of the Queensway Gateway Road (QGR) Post-Project Appraisal.”
- “Note the principal programme, financial and technical challenges encountered during completion of the scheme, together with the measures undertaken to manage construction safety, traffic management, road safety and the associated disruption.”
- “Consider the lessons learned from the delivery of QGR.”
In plain English
Recommended · Officers have advised a course of action. Members decide.
A report to Place Scrutiny Committee's meeting of 30 November 2026 reviews the development and delivery of the Queensway Gateway Road, recommending that members note the findings and conclusions of the project appraisal and consider the lessons learned from its delivery. p1p2p3p4p5p7
Traffic management was in place across seven periods totalling 41 weeks between September 2024 and October 2026, and the council says it recognises the disruption this caused to businesses, residents and road users. p23p33
The report sets out lessons for future infrastructure schemes, including clearer third-party delivery responsibilities, stronger contractor accountability and earlier escalation of delivery concerns. p47p56
Show the 10 passages this is based on
- p1Report to: Place Scrutiny Committee Date of meeting: page 1 ↗
- p230 November 2026 By: Director of Communities, Economy and Transport page 1 ↗
- p3Title: Queensway Gateway Road – Post Project Appraisal page 1 ↗
- p4Purpose: To provide the Committee with a review of the development and delivery of the Queensway Gateway Road. page 1 ↗
- p5RECOMMENDATIONS: (1) Note the findings and conclusions of the Queensway Gateway Road (QGR) Post-Project Appraisal; page 1 ↗
- p7(3) Consider the lessons learned from the delivery of QGR. page 1 ↗
- p233.2 The traffic management schedule below lists seven periods totalling 41 weeks: 33 weeks of daytime arrangements and eight weeks of nighttime working between September 2024 and October 2026. The extent and location of restrictions varied; this total does not mean that all affected roads were continuously restricted for 41 weeks. Initial arrangements affected the A21 Sedlescombe Road, Maplehurst Road and Junction Road/The Ridge. A banksman maintained public access to the SEAT garage. Later nighttime arrangements used shorter A21 traffic management sections. The County Council recognises the disruption experienced by businesses, residents and road users over this period. page 3 ↗
- p33Seven recorded periods 41 weeks 3.3 ESH-C, as Principal Contractor, developed and implemented traffic management and safe working arrangements in coordination with the County Council and NH. The initial arrangements supported preparatory work and site investigations, which were critical to informing later construction, as well as works affecting Junction Road and the A21. The programme changed as approvals, access and site conditions were resolved. The County Council reviewed arrangements with ESH-C and NH to maintain safe access and reduce disruption as work permitted. The duration of each restriction should be considered against the activities and safe working requirements applying at that time. page 3 ↗
- p475.2 The delivery of QGR highlighted some shortcomings in contractor management continuity, subcontractor coordination and the reliability of third-party programme and financial information. These issues affected the Council’s ability to maintain a consistent understanding of progress, emerging risks and forecast costs, requiring greater direct involvement in coordinating delivery and resolving issues with ESH-C and NH. In addition, the complexity and timescales associated with third-party approvals, access arrangements and utility works had a significant impact on the programme and sequencing of works, additional traffic management requirements were necessary, along with addressing the seasonality impacts of the construction works. The experience reinforces the importance of establishing a clear understanding of outstanding risks, liabilities and dependencies when inheriting an incomplete scheme, alongside stronger contractor accountability, reliable reporting and earlier escalation of delivery concerns. page 5 ↗
- p56Future schemes should maintain clear third-party responsibilities, coordinated approvals and dependencies, contractor accountability, reliable reporting and formal close-out. page 6 ↗
Places and organisations it names
Other papers for this meeting
- APPENDIX 2: Financial Expenditure and Forecast Outturn
- Place Scrutiny Committee agenda
- Appendix 1: Place Scrutiny HWRS review findings
- Appendix 1: QGR final design and construction phasing (R1.2)
- Appendix 1 ESCC Proposed Revised Strategic Asset Plan 2026-2029
- Appendix 2: Terms of Reference HWRS booking system review
- Appendix 2 ESCC Property Asset Register October 26
- Appendix 3 SPACES Programme Update November 26
- ESCC Strategic Asset Plan 2026-2029 and related Property service updates
- Forward Place decisions 30 Nov 2026
- Minutes of the previous meeting
- Place Committee work programme November 2026
- Printed plan Forward Plan 1 November 2026 - 28 February 2027 Forward Plan
- Scrutiny Review of the Household Waste Recycling Site booking system
- Work programme