Eastbourne Town Centre Phase 2A Experimental Traffic Regulation Orders

Committee report · Lead Member for Transport and Environment · Mon 16 Mar 2026 · East Sussex County Council · the whole meeting

Read the council's document ↗

What it recommends

In the report's words. A recommendation is a proposal, and the meeting can agree, change or reject it.

What the meeting decided

The minutes record: Agreed. “RESOLVED to: (1) note the previous development work that has been undertaken in relation to the Eastbourne Town Centre Movement and Access Package 2a, Terminus Road (Cornfield Road to Langney Road); and (2) agree that Experimental Traffic Regulation Orders are advertised post construction in relation to vehicular access and timings within the Eastbourne Town Centre Movement and Access Package Phase 2a project.” minutes ↗

In plain English

Each sentence was checked against the passage it cites. How the checking works.

Recommended · This went to the meeting on Mon 16 Mar 2026. What was decided is in that meeting's minutes.

East Sussex County Council received £8m from the South East Local Enterprise Partnership Local Growth Fund towards the Eastbourne Town Centre Movement and Access Package. p7

The scheme began construction in September 2025 and is currently scheduled to be completed by August 2026. p15

The ETRO will operate for at least 6 months, during which feedback will be collected to determine the suitability of the proposed access hours. p36

We’ve left out 1 more sentence of this summary because it didn’t pass our check against the paper.

Show the 3 passages this is based on
  • p71 Background 1.1 East Sussex County Council received £8m from the South East Local Enterprise Partnership (SELEP) Local Growth Fund towards the Eastbourne Town Centre Movement and Access Package. £5m funded Phase 1 (Terminus Road, Cornfield Road, Gildredge Road, to support the Beacon shopping centre extension), completed in 2020/21. After SELEP approved a further business case in February 2019, £3m was allocated towards the completion of Phase 2a (Terminus Road: Bankers Corner, Bolton Road, Langney Road). page 1 ↗
  • p151.5 The scheme began construction in September 2025 and is currently scheduled to be completed by August 2026. Experimental Traffic Regulation Orders (ETROs) and Traffic Regulation Orders (TROs) will be needed for the scheme’s operation, with public consultations held before any permanent changes. page 2 ↗
  • p362.10 To support these timescales officers are seeking agreement to pilot the hours of access under an ETRO following the completion of construction, allowing assessment of optimal timings for local traders and residents. The ETRO will operate for at least 6 months, during which feedback will be collected to determine the suitability of the proposed access hours. page 3 ↗

Places and organisations it names

Other papers for this meeting

This page collects what Open Hastings knows about the council's document. If something here is wrong, we correct it here and log it on the about page.