Appendix 1 Corporate Summary - 29.09.2026
In plain English
Noted · Received for information; no decision followed.
Cash investment balances fell by 52% in a year, from £137.2m to £65.5m, while the Council's external debt stood at £198.1m, held as long-term loans with the Public Works Loan Board. p108
There were no requested changes to fees and charges during the quarter. p128
The value of debt aged over five months decreased by £1.485m to £12.978m, compared with £14.463m at the end of 2025/26. p129
Most of this debt, £12.502m, relates to Adult Social Care and Health, which decreased by £1.027m during the quarter. p130
Show the 4 passages this is based on
- p108- - Total Funding 97,978 97,978 0 - - - Treasury Management The Treasury Management Strategy, which provides the framework for managing the Council’s cash balances and borrowing requirement, continues to reflect a policy of ensuring minimum risk, whilst aiming to deliver secure realistic investment income on the Council’s cash balances. Cash investment balances as at 30 June 2026 have fallen by 52% in 1 year, from £137.2m at Q1 2025/26 to £65.5m at Q1 2026/27. The average level of Council funds available for investment purposes during Q1 was £34.9m. The total amount received in short term interest for Q1 was £349k at an average rate of 4.01%, compared to £527k at an average rate of 4.19% for Q4 2025/26. The Bank of England Base Rate during Q1 remained unchanged at 3.75%. During Q1, no fixed term deposits with local authorities or banks were placed. The investment strategy adopted in previous quarters, which focused on ‘laddering’ deposits, has resulted in a steady and well‑balanced maturity profile. However, during Q1, short‑term borrowing was required to manage in‑year cashflow pressures. This borrowing was sourced from the local authority market via a Council approved broker. The total cost of this short‑term borrowing was £25.5k, incurred at an average interest rate of 4.18%. All short-term borrowing was repaid before 30 June 2026. Cashflow is monitored through a rolling 24 month forecast. Current projections assume that once our existing investments mature these will not be reinvested for a fixed term, with funds instead remaining instantly accessible, which will help manage cashflow. The Council’s external debt, totalling £198.1m at Q1, is held as long-term loans and is fully with the Public Works Loan Board (PWLB). A £2m loan with the PWLB matured on the 30 June 2026, at a rate of 7.125% and no further long-term borrowing was undertaken in Q1.
- p128There were no requested changes to fees and charges during the quarter. Outstanding debt analysis (£ millions)
- p129The value of debt aged over five months at Q1 has decreased by £1.485m to £12.978m compared with £14.463m at the end of 2025/26.
- p130The majority of this debt, £12.502m (96.33%), relates to Adult Social Care and Health (ASCH) which has decreased by £1.027m at Q1, compared with £13.529m at the end of 2025/26. ASCH client debt continues to be the Council’s largest area of debt collection activity. While recovery can be protracted due to the complexity and sensitivity of individual circumstances, the reduction in aged debt demonstrates the positive impact of ongoing improvements to the collection and recovery of ASCH client contribution income following a strategic review of the end-to-end income collection and debt recovery process. The earlier issuance of payment reminders, implemented during Q1 as one of the recommendations arising from the review, has supported more timely engagement with service users, enabling non-payment to be addressed more promptly.
Places and organisations it names
Other papers for this meeting
- Cabinet agenda
- Appendix 1, Cabinet
- Appendix 1, Cabinet
- Appendix 1, item 8a
- Appendix 1, item 8b
- Appendix 1, item 9a
- Appendix 1, item 9b
- Appendix 1 - East Sussex External Assurance Review 2026 CB
- Appendix 2, Cabinet
- Appendix 2 - CIPFA action plan updates Cabinet 29.09.26
- Appendix 2 TM Prudential Indicators - 29.09.2026
- Appendix 3 - Priority and delivery outcomes Cabinet 29.09.26
- Appendix 3 ASCH - 29.09.2026
- Appendix 4 BSD - 29.09.2026
- Appendix 5 CSD - 29.09.2026
- Ashdown Forest Trust Fund
- Climate Resilience and Environment Policy
- Council Monitoring Report - Q1 2026/27
- Minutes of the meeting held on 21 July 2026
- Reconciling Policy, Performance and Resources (RPPR): Update on planning for 2027/28
- Scrutiny Review of Personal Travel Budgets and Independent Travel Training in Home to School Transport - Observations on the Scrutiny Committee's report
- Scrutiny Review of Personal Travel Budgets and Independent Travel Training in School Transport - Report of the People Scrutiny Committee
- Scrutiny Review of Street Works - Observations on the Scrutiny Committee's report
- Scrutiny Review of Street Works - Report of the Place Scrutiny Committee